Office building site installationI. Matters to be noted when the containers arrive: (1) The structural secondary beam can not be used as the focus point of transportation. (2) Before unpacking the goods and unfastening the fixed rope, the goods must be fixed firmly with support pieces to prevent toppling. (3) #1-3 Stair pieces, please note that the holes at the top of the boxes cannot be trampled. (4) Attention should be paid to the glass protection of doors and windows while transferring and hoisting. II. Introduction to installation steps: 1. The first floor: review the foundation ---- site determination of vehicles and crane stations, crane entering Hoisting the first container, adjusting and correcting the box position, Hoisting of the second container, adjusting the position, welding with the foundation ----...... ---- Mounting of the last case body ---- double core square inch ---- mounting of the case body connecting plate ---- The waterproofing at the top of the container body ---- the waterproofing treatment on the side of the container body ---- the top of a layer of the box body The laying of waterproof coil ---- the installation of on-site water supply and drainage, the installation of strong and weak electricity ---- the top opening At the setting of waterproof measures, a layer of roof waterproof (see roof waterproof practice) ---- box enclosure The ground of the hall is backfilled and tamped, and the cement mortar is levelled with the bottom plate of the box. ---- internal installation repair ---- handles the waterproofing of the side openings; 2. The second floor: determination of vehicles and crane stations ---- crane approach ---- Transportation vehicles Second approach ---- Clear the temporary rainproof facilities on the top of the first floor ---- lift and adjust the first container Correct the position of the box body and connect it with the first layer of the container body ---- Hoisting of the second container body, adjusting the overall position, Connection with a layer of housing ----...... ---- The hoisting of the last piece of container ---- Recheck the dimensions ---- Installation of connecting plates of the container body ---- second floor monolithic wall installation ---- monolithic roof installation ---- Monolithic wall window installation ---- outdoor platform bottom frame installation, balustrade installation, internal stairs End mounting ---- Waterproof treatment on top of case ---- Waterproof treatment on side of case ---- on-site Installation of water supply and drainage, installation of strong and weak electricity ---- internal decoration ---- side hole waterproof;
|